Guide · Energy & Efficiency
Compressed Air Energy Audit
A practical, step-by-step guide to auditing an industrial compressed-air system — find leaks, fix sequencing and unloaded running, and quantify the kWh, £ and tCO₂e savings worth chasing.
Why audit compressed air
Compressed air is typically the single most expensive utility on an industrial site, and 20–30% of the electricity used to make it is wasted — through leaks, poor sequencing of multiple compressors, and machines running unloaded out-of-hours. A structured energy audit turns that hidden waste into a ranked, costed action list.
What you need before you start
- An inventory of every compressor: tag, rated kW, control type (fixed-speed, VSD, modulating), unloaded kW if known.
- Power (kW) logging on each compressor at 1–15 minute intervals for at least two weeks — ideally a full production cycle.
- The site electricity tariff (£/kWh) and grid carbon intensity (kgCO₂e/kWh) so findings can be monetised.
- Production schedule and shift hours so out-of-hours running can be detected reliably.
Step 1 — Establish the baseline
Plot total kW for the whole compressor house across the observation window. Identify the overnight / no-demand baseline (the floor the system never drops below). Anything drawn during zero-production hours is, by definition, not making useful air — it is leakage plus unloaded running.
Step 2 — Classify every interval
For each compressor and timestamp, label the state as off, unloaded, or loaded using power thresholds (e.g. unloaded ≈ 25–35% of rated kW for a fixed-speed screw). This lets you compute run-hours, unloaded fraction, start/stop counts, and overlap between machines.
Step 3 — Quantify leaks
Annualise the overnight baseline kW to 8,760 hours. Above a modest threshold (typically 5–10% of average loaded demand), the surplus is attributable to leaks. A tag-and-fix programme on a site drawing 12 kW of leakage saves on the order of ~52,500 kWh/yr — at £0.25/kWh, ~£13,000 and ~11 tCO₂e per year.
Step 4 — Check sequencing and unloaded running
When more than one compressor runs at the same time, a healthy system keeps one fully loaded as the base unit and trims with a VSD. If overlap intervals routinely show no fully-loaded unit, you have a sequencing problem — usually solved with a master controller. Excessive unloaded running on a fixed-speed unit is a strong indicator that a VSD retrofit or better sequencing will pay back fast.
Step 5 — Catch out-of-hours running and short cycling
Cross-reference compressor state with the shift schedule. Any run-time outside production is a candidate for a timer or isolation valve. Compressors starting and stopping more than ~6 times per hour are short-cycling — symptomatic of an undersized receiver or wrong pressure-band setup, and a cause of motor wear and transient energy losses.
Step 6 — Monetise and rank
Convert each kWh saving to £ at the site tariff and to tCO₂e at the grid carbon factor, then rank findings by annual £ saving. That ranked list — with rationale, threshold used, and an indicative payback — is the deliverable an engineering team can act on.
The ruleset, in one line each
- Leak burden — overnight baseline above threshold = leakage.
- Out-of-hours running — run-time outside production hours.
- Excessive unloaded — fixed-speed unit unloaded too much of its run-time.
- Poor sequencing — overlap intervals with no fully loaded base unit.
- Short cycling — starts/hour above threshold.
Run this audit on your own data
CompressIQ automates every step above. Upload your compressor kW logs, configure tariff and shift hours, and the analysis engine produces the ranked findings list and a PDF report with the rationale and thresholds for each one.